TRANSIT PROJECT ASSESSMENT PROCESS (TPAP) SCHEDULE
KEY MILESTONE |
DATE |
---|---|
Pre-TPAP Phase |
October 2015 to April 2018 |
Notice of Commencement of TPAP (120-day period) |
April 25, 2018 |
Notice of Completion of Environmental Project Report (EPR)/EPR Available for Review |
August 23, 2018 |
Agency/Stakeholder and Public Review Period (30 days): |
August 23, 2018 to September 24, 2018 |
Minister of the Environment, Conservation and Park's Decision (35 days): |
September 25, 2018 to October 29, 2018 |