TRANSIT PROJECT ASSESSMENT PROCESS (TPAP) SCHEDULE


KEY MILESTONE

DATE

Pre-TPAP Phase

October 2015 to April 2018

Notice of Commencement of TPAP (120-day period)

April 25, 2018

Notice of Completion of Environmental Project Report (EPR)/EPR Available for Review

August 23, 2018

Agency/Stakeholder and Public Review Period (30 days):

August 23, 2018 to September 24, 2018

Minister of the Environment, Conservation and Park's Decision (35 days):

September 25, 2018 to October 29, 2018